Construction Updates

May 2010 Monthly Look Ahead Schedule

Traffic Management

S.R. 82 Traffic Shift Begins Sunday, June 13
– Westbound S.R. 82 Travel Lanes will Shift
Beginning Sunday (June 13),
westbound travel lanes on S.R. 82 will shift to the south from approximately Teter Road to Ortiz Avenue. Beginning at 7 a.m. on Sunday, crews will begin restriping the roadway. One eastbound travel lane through this area will be closed so that the restriping can take place. This lane closure is expected to last until the entire area is restriped (throughout the day and into Sunday night). Motorists may experience travel delays Sunday until crews complete the lane shift work.

There will be two travel lanes open in each direction after the traffic shift is completed (sometime Sunday night before 6:00 am Monday morning). This traffic shift is expected to remain in place for approximately three months. Crews will be reconstructing the new westbound travel lanes of S.R. 82 as part of the City of Fort Myers’ S.R. 82 Widening Project. Motorists are advised to USE CAUTION driving in this area.

Survey
Locate existing utilities and stakeout future utility lines on the north side of S.R. 82.

Clearing & Grubbing
Clearing and grubbing is complete.

Right-of-Way
Installation of silt fence as required along the north side of S.R. 82 and pond perimeters. 
Silt fence to be installed to Colonial Boulevard by end of the month.

Utilities
Force Main
Pressure testing of Phase I Force Main line.  All testing expected to be complete by the end of April. Water Main
Pressure testing of Phase I Water Main line.  All testing expected to be complete by the end of April.