Construction Updates


RoadWatch Advisory for the
City of Fort Myers S.R. 82 Widening Project
May 10, 2012

LEE COUNTY

S.R. 82: from Ortiz Avenue to Lee/Colonial Boulevard

Beginning at 8 p.m., Monday night, May 14, eastbound travel lanes on S.R. 82 will shift to the south side of the roadway from Ortiz Avenue to Forum Boulevard. Motorists should expect intermittent stopping and travel delays Monday night until crews complete the lane shift work. (This traffic shift was originally scheduled for Sunday night, but due to inclement weather has been rescheduled for tonight.)

There will be two travel lanes in each direction after the traffic shift is completed (sometime Monday night before 6:00 am Tuesday morning). Eastbound travel lanes will merge into one lane just west of Forum Boulevard. Westbound travel lanes will remain the same. At the time of this traffic shift and in the future, there will be a right-turn in, a right-turn out and a directional left turn into Destination Drive and Teter Road.

Crews will be reconstructing the median of S.R. 82 as part of the City of Fort Myers’ S.R. 82 Widening Project. Motorists are advised to USE CAUTION while driving in this area.

Travel lanes on Colonial/Lee Boulevard through the intersection with S.R. 82 are shifted south to the newly constructed roadway.

Southbound travel lanes on S.R. 82 are shifted to the east at the intersection of S.R. 82 and Colonial/Lee Boulevard. There is one travel lane in each direction on S.R. 82 from Colonial/Lee Boulevard to Forum Boulevard. There are two westbound travel lanes open from Forum Boulevard to Ortiz Avenue. Motorists are advised to USE EXTREME CAUTION driving in this area. Crews are reconstructing the new southbound travel lanes of S.R. 82.

Spring 2012

Traffic is shifted to the north side of SR 82 from Ortiz Avenue through the Colonial/Lee Boulevard intersection.

Traffic is shifted to the east side of Colonial/Lee Boulevard while crews construct the west sides of the SR 82 and Colonial/Lee Boulevard intersection.

Traffic is shifted from Old Buckingham Road to the newly constructed Buckingham Road.

Crews continue to install storm drainage and pave the south side of SR 82. Crews continue to construct the sidewalk along the project.



March 2012
January 2012
December 2011
November 2011
October 2011
August 2011
July 2011
June 2011
March 2011
October 2010
September 2010
July/August 2010
May 2010
April 2010
March 2010
February 2010