Construction Updates

April 2010 Monthly Look Ahead Schedule

Traffic Management
S.R. 82 westbound travel lanes will be reduced from three lanes to two lanes from east of Park 82 Drive west to Ortiz Avenue.

Survey
Locate existing utilities and stakeout future utility lines on the north side of S.R. 82.

Clearing & Grubbing
Clearing and grubbing is complete.

Right-of-Way
Installation of silt fence as required along the north side of S.R. 82 and pond perimeters. 
Silt fence to be installed to Colonial Boulevard by end of the month.

Utilities
Force Main
Pressure testing of Phase I Force Main line.  All testing expected to be complete by the end of April. Water Main
Pressure testing of Phase I Water Main line.  All testing expected to be complete by the end of April.